Report of Edward H. Tracy, Esquire, Civil Engineer.
Table of Contents

Title Page
Table of Contents
Maps Accompanying this Report
Copy of a Report of a Committee of the Honorable the Executive Council, dated 18th October, 1854, approved by His Excellency the Governor General, in Council, on the same day.
Instructions for J. B. Jarvis, Esquire, Civil Engineer, on the subject of a Canal between the River St. Lawrence and Lake Champlain.
STATEMENT shewing the Cost of a Survey for a Canal to connect the River St. Lawrence with Lake Champlain.
Report of Edward H. Tracy, Esquire, Civil Engineer.
[Report]
ESTIMATE of Cost of the proposed St. Lawrence and Champlain Canal.
Report of John B. Jarvis, Esquire, Civil Engineer.
Report of Messrs. Maillefert and Raaslof, Civil Engineers, upon the Examination and Survey of the River St. Lawrence, from Prescott to the head of the Lachine Canal, and certain experimental blasting operations made during the summer of 1854.
Table A.

ESTIMATE of Cost of the proposed St. Lawrence and Champlain Canal.

First,-By enlarging Chambly Canal, and improving the navigation of the River Sorel.
Dredging bars in River between Rouse's Point and St. Johns 140,000 cubic yards @ 25c. $35,000
New Pier at St. Johns. 50,000
Excavation of earth 1,786,000 " @ 30c. 535,800
" " 470,000 " @ 20c. 94,000
" rock 107,000 " @ $1.25c. 133,750
" " 112,000 " @ 75c. 84,000
River Wall, 32,000 " @ $1.00c. 32,000
25,600 " @ $1.50c. 38,400
Stone filling 14,600 " @ 75c. 10,950
Crib Work 1,105,000 cubic feet @ 4c. 44,200
Clearing out River Reach and building new Tow Path 13,600 lineal feet @ $1.00c. 13,600
New Road 2 miles @ $1,000 2,000
Two Stone Culverts 12,100
One Waste Weir 5,000
Seven Draw Bridges 7 @ $3,000 21,000
Lockage 73 feet @ $5,000 365,000
One Guard Lock 40,000
Pier at Chambly 5,000
Stone Protection Wall inside of Canal 11.8 miles @ $20,000 236,000
Raising St. Ours Dam 4 feet and lengthening Lock 75,000
$1,832,800
Add for Contingencies and Engineering, ten per cent 183,280
Total Cost $2,016,080

Second,-By enlarging part of the Chambly Canal, and building new Canal for the remainder of the distance to Lorgueuil.
Dredging bars in River between Rouses Point and St. Johns 140,000 cubic yards, @ 25c. $35,000
New Pier at St. Johns 50,000
Excavation of earth 1,484,000 " @ 30c. 445,200
" " 106,000 " @ 25c. 26,500
" " 3,650,000 " @ 20c. 730,000
" rock 107,000 " @ $1.25c. 133,750
" " 276,000 " @ $1.00c. 276,000
" " 112,000 " @ 75c. 84,000
River Wall 32,000 " @ $1.00c. 32,000
" 25,600 " @ $1.50c. 38,400
" 2,700 " @ $2.00c. 5,400
Stone filling 14,600 " @ 75c. 10,950
Crib Work 1,105,000 cubic feet, @ 4c. 44,000
Clearing out River Reach and building new Tow Path 13,600 lineal feet @ $1.00c. 13,600
New Road 2 miles @ $1,000 2,000
One Waste Weir 5,000
Eight Culverts 44,200
One Guard Lock 40,000
Lockage 72 feet @ $5,000 360,000
Six Sluices 6 @ $5,000 30,000
Montreal River Aqueduct 39,000
One Railroad Draw Bridge 5,000
Fourteen Road Bridges 14 " @ $3,000 42,000
Pier at Longueuil 100,000
Stone Protection Wall inside of Canal 28.28 miles @ $20,000 565,600
$3,157,660
Add for Contingencies and Engineering, ten per cent 315,760
Total Cost $3,473,360

Third.-By enlarging part of the Chambly Canal, and building new Canal for the remainder of the distance to Caughnawaga.
Dredging bars in River between Rouse's Point and St. Johns 140,000 cubic yards @ 25c. $35,000
New Pier at St. Johns 50,000
Excavation of earth 1,484,000 " @ 30c. 445,200
" " 1,534,000 " @ 25c. 383,500
" " 3,263,000 " @ 20c. 652,600
" rock 107,000 " @ $1.25c. 133,750
" " 222,000 " @ $1.00c. 222,000
" " 112,000 " @ 75c. 84,000
River Wall 32,000 " @ $1.00c. 32,000
" 10,000 " @ $1.00c. 10,000
" 25,600 " @ $1.50c. 38,400
" 2,700 " @ $2.00c. 5,400
Stone filling 14,600 " @ 75c. 10,950
Crib Work 1,105,000 cubic feet @ 4c. 44,200
Clearing out River Reach and building New Tow Path 13,600 lineal feet @ $1.00c. 13,600
New Road 2 miles @ $1,000 2,000
Waste Weir 5,000
Two Sluices round Locks 2 feet @ $5,000 10,000
Nine Culverts 62,500
Montreal River Aqueduct 39,000
St. Phillippe " 21,000
La Tortue " 36,000
St. Pierre " 21,000
Guard Lock 40,000
Lockage 25 feet @ $5,000 125,000
Two Sluices 2 @ $5,000 10,000
Two Railroad Bridges 2 @ $5,000 10,000
Twenty-one Road Bridges 21 @ $3,000 63,000
Pier at Caughnawaga 50,000
Altering Railroad 25,000
Stone Protection Wall inside of Canal 34.46 miles @ $20,000 689,200
_______ $3,369,300
Add for Contingencies and Engineering, ten per cent 336,930
Total Cost $3,706,230

Fourth.--By building a Canal from St. John to Caughnawaga, on a direct line, with a Navigable Feeder from the Beauharnois Canal.
Dredging bars in River between Rouse's Point and St. Johns 140,000 cubic yards a 25c. $35,000
New Pier at St Johns 20,000
Excavation of earth 1,700,000 " @ 25c. 425,000
" " 3,950,000 " @ 20c. 790,000
" rock 50,000 " @ $1,00c. 50,000
Montreal River Aqueduct 39,000
St. Phillippe " 21,000
La Tortue " 36,000
St. Pierre " 21,000
Ten Culverts 85,000
Lockage, 100 feet @ $5,000 500,000
Sluices, 8 @ $5,000 40,000
Two Railroad Bridges 2 @ $5,000 10,000
Twenty-five Road Bridges 25 @ $3,000 75,000
Protection Wall inside of Canal 25.57 miles @ $20,000 511,400
Pier at Caughnawaga. 50,000
_______ $2,768,400
Add for Contingencies and Engineering, ten per cent 270,840
Total Cost without Feeder, $2,979,240
NAVIGABLE FEEDER.
FROM BEAUHARNOIS CANAL.
Excavation of earth 790,000 cubic yards @ 25c. $197,500
" 1,951,000 " @ 20c. 390,200
Chateauguay Aqueduct 125,000
St. Louis " 60,000
Ten Culverts 10 45,000
Ten Road Bridges 10 @ $3,000 30,000
Stone Protection Wall inside of Canal 16.19 miles @ $20,000 323,800
_______ $1,171,500
Add for Contingencies and Engineering, ten per cent 117,150
$1,288,650
Cost of Line without Feeder, 2,979,240
Total Cost, $4,267,890

Fifth.--By building a Canal from St. Johns to Caughnawaga on a direct line, with a Feeder from the Beauharnois Canal, that is not navigable.
As above $2,979,240
Feeder from Beauharnois Canal, not navigable.
Excavation of earth 790,000 cubic yards @ 25c. $197,500
" 1,951,000 " @ 20c. 390,200
Chateauguay Aqueduct 125,000
St. Louis " 60,000
Ten Culverts 10 45,000
Ten Road Bridges 10 30,000
Total as in last account, $847,700
Say for Feeder, not navigable, cost one-third of the above, or 280,000
Add ten per cent as before 28,000
$308,000
Total Cost, $3,287,240

Sixth.-By building a Canal from St. Johns to Beauharnois, on a direct line, without branch to Caughnawaga.
Dredging bars in River between St. Johns and Rouse's Point 140,000 cubic yards, @ 25c. $35,000

 